Project consists of procurement of major electrical equipment to
replace two existing substations at the County Authority
Industrial Pretreatment Plant.
Board meetings and strategic plans from Lehigh County (Water And Sewer) Authority
Lehigh County Authority Board Board Meeting
Date: Oct 12, 2026Type: Meeting mention
The board meeting focused on several key items including the presentation of a final budget proposal for 2027, which addressed new industry impacts, staff additions, and rate adjustments. Discussions covered the upcoming rebranding roll-out, including signage and trademarking costs. The board also reviewed the scope of a strategic plan refresh, emphasizing the need to focus on employee safety culture following recent safety performance metrics. Finally, the board received an educational overview of key financial metrics such as operating ratios, debt service coverage, and capital coverage ratios.
Lehigh County Authority Board Of Directors Board Meeting
Date: Sep 28, 2026Type: Meeting mention
The board reviewed the preliminary 2027 budget, focusing on labor costs, inflation projections, and revenue impacts related to wastewater flows and industrial customers, specifically Chobani and Boston Beer. Discussions covered current industrial sampling charges, capital budget requirements, and borrowing plans for the upcoming fiscal year. Additionally, the board scheduled an executive session to address a cybersecurity matter.
Lehigh County Authority Board of Directors Regular Meeting Minutes
Key Contacts
Public-sector contacts connected to Lehigh County (Water And Sewer) Authority.
The meeting focused on the preliminary 2027 budget review, highlighting strategic initiatives, staffing plans, and projected inflationary impacts. Key business included the authorization of PENNVEST funding for a PFAS treatment facility, the approval of the construction phase for the Lead Service Line Replacement Project Cycle 3, and the procurement of equipment for the Water Filtration Plant PFAS treatment. Additionally, the board reviewed the results of the Lead Service Line Replacement Project Cycle 1, discussed the Schantz Spring WFP Interconnection project, and examined the second-quarter capital project update report.
Extracted from official board minutes, strategic plans, and video transcripts.
Meeting signals
Know what buyers discuss before RFPs drop
Track Lehigh County (Water And Sewer) Authority meetings, strategic plans, and budget discussions before the public bid appears.